Onslow Quarry - RJV

Onslow Quarry

Onslow Quarry

2012 - 2014
Onslow Western Australia, Australia
Thiess & BEST JV

Overview

Supply & delivery of quarry material to Wheatstone Project.

Detail

The 2 year contract was awarded in August 2012 to produce and supply quarry material to Thiess and BEST JV for the Wheatstone Project at Onslow.

A 20km sealed access road including MRD intersection with Onslow Road was constructed by RJV within 12 weeks of mobilisation to allow timely haulage for the delivery of the quarry products to the Wheatstone Project.

2.7 million tonnes of various quarry material were produced and delivered over the 2 year contract.

The team’s experience adds great strength and expertise in road construction, quarrying, crushing and screening, and haulage management.

Typical rock material produced:

  • Basecourse
  • Subbase
  • Geocell rock
  • Granular fill
  • Drainage aggregate
  • Quarter tonne
  • 1-3 tonne
  • 2-4 tonne
  • 3-6 tonne