Boddington

Client

Newmont

Total Project Value

$28M

RJV Scope

Waste Dump Expansion

Project Location

Boddington, Western Australia

Project details

Construction of 300 HA Waste Dump at the Boddington Gold Mine for Newmont.

Contract value of $28M with duration of two years that commenced in March 2016.

Scope of Work was bulk earthworks including:

  • clearing,
  • construction of drains
  • mining of gravel
  • construction of mine water and run-off dams

Areas within the construction site had been determined as Dieback areas requiring strict control over machine movements within the site and plant cleaning when moving from one zone to another.